Project and Funding Statuses
Four Months Ago, Five Hydrogen Hubs that Faced Potential Termination were “Retained”: Here’s What We Know
By Keith Boyea, OCED Alum
August 5, 2026
On April 14, 2026, the U.S. Department of Energy (DOE) released a list of “retained” projects that were previously considered for termination. Five Hydrogen Hub projects (hubs) were on that list. These five hubs represent a multi-billion dollar investment in the hydrogen economy, and represent a significant opportunity to advance hydrogen production in the U.S. Four months later, DOE alums dug in and looked into the question – what would it look like to restart the hubs projects and what has the DOE actually done since April?
What are Hydrogen Hubs?
Congress appropriated $8 billion for hydrogen hubs in the Infrastructure Investment and Jobs Act (IIJA) of 2021. The money was appropriated to a new office, called the Office of Clean Energy Demonstration (OCED), which quickly stood up and started work on the hubs. The process to award took some time–the funding opportunity that was released in September 2022 was the largest funding opportunity anyone at DOE could remember–but the last hub was awarded in January 2025. Seven hubs were ultimately awarded and they are summarized in the table below:
A Very Brief History of DOE Hydrogen Hubs Under the Trump Administration
In early 2025, DOE issued internal guidance that stopped work on nearly every OCED project issued under IIJA and the Inflation Reduction Act (IRA), including the hubs, pending a series of reviews. OCED lost 85% of its staff to the Deferred Resignation Program. Every invoice required a political appointee’s approval for payment, which is a significant departure from past practice.
Based on the reviews, in May 2025, 24 OCED projects with $3.5 billion in Federal funding were terminated. Then, in October 2025, 16 more OCED projects, worth $3.3 billion in funding, including two Hydrogen Hubs–Arches and Pacific Northwest–were terminated by DOE, because they were based in “blue states”. The other five hubs showed up on a leaked list of projects DOE intended to terminate in the future. DOE never formally took action on the leaked list, but during the review period, the projects stopped entirely, and experienced very little communication from DOE. In other words, they were “ghosted.” Then in April of this year, DOE announced that its review process was completed and the five threatened hubs from the leaked list were being retained. Now that DOE has made a decision to retain these five hubs, we should expect to see signs of these projects restarting.
What has Reinstatement Actually Meant?
Based on publicly available data, it appears that the retained hubs continue to experience ghosting. Here are some indicators of continued ghosting:
According to the USASpending.gov, the most recent modification to a hydrogen hub contract occurred on April 8, 2026. That modification pre-dates the April 14th retention date. This means that no hub contract has been modified to reflect the retention.
Four recipients received payments in late May or early June of 2026, but invoices are typically for work at least 30 days in the past, so these invoices paid for work that likely happened prior to the April 2026 retention announcement. These payments were relatively small–the largest being about $130,000–which suggests that project execution is still moving very slowly. The first phase of these projects are expected to cost DOE upwards of $30 million; this far into a planning phase DOE should expect much larger payments.
Total payments to the hubs reflects only 26% of what was obligated to complete phase one. Post reinstatement, payments have not accelerated as one would have expected. In some cases, payments have not been made at all. In fact, at the current pace of outlay, some hubs will not finish Phase I until 2032.
The reinstated hubs have made no public statements about new engagement from DOE. Certainly, the hubs are under no obligation to make any statement, but given the number of stakeholders involved, one may have expected at least one hub to publicly signal a new approach from DOE.
The Office of Management and Budget’s (OMB) most recent apportionment spend plan for DOE, released on July 17, 2026, indicates that the agency intends not to spend additional funds on the Hydrogen Hubs this year.
What Should Reinstatement Mean?
Secretary Wright indicated in April congressional hearings that the hubs would be retained. Here are actions that we are monitoring for evidence of retentions and project execution going forward:
Update the hubs contracts to reflect the delay. By the end of August 2026, DOE expected all of the hubs to have completed Phase I. To our knowledge, no hub has completed Phase I. Much of this delay is attributable to the stop-start-ghost roller coaster that the hubs projects have been on since January 2025. The contracts need to be updated to reflect the new schedules for completion of the phases.
Update the hubs contracts to reflect administration priorities. The administration has expressed its clear preference for fossil fuel over renewable energy. Some of the hubs relied heavily on renewables and some did not. Carbon capture technologies were a key feature of hubs–is that still a priority? For other projects retained by the Department, there has been a pattern of shifting scope to reflect administration priorities and as a result, it’s anticipated that reinstatement of these projects may reflect this pattern as well. It is worth noting that all the hubs contracts included Go/No-Go factors related to community benefits. If community benefits are no longer an administration priority–and they probably are not priorities since diversity, equity and inclusion were part of community benefits–these elements need to be removed from the contracts.
Update the hubs contracts to reflect changes in the hydrogen economy. The hydrogen economy is in a significantly different place than it was when DOE released the original solicitation in September 2022. DOE needs to explore what the hydrogen economy looks like in 2026 and where it expects that economy to go in the 2030s. There was significant enthusiasm for hydrogen from 2022 to 2024 with investment in the hubs and enactment of the clean hydrogen production tax credit, but that enthusiasm has seemed to wane. Might DOE refocus its ambitions for hydrogen hubs? Maybe or maybe not, but either way, it would be worthwhile for DOE to bring its experts together to try to figure this out. Once that’s done, that revised ambition needs to find its way into the hubs contracts.
Update Subprojects. Most of the hubs depended on what OCED called, “subprojects.” These were, effectively, separate construction projects inside the larger hub. As the projects matured through the planning stage, OCED expected subprojects to move in and out of the hub. To date, no new subprojects have been announced, while several subprojects have dropped out. In order to ensure the projects are able to retain their value and impact, DOE could direct the hubs recipients to actively seek new subprojects to replace the lost subprojects. Under the previous administration, DOE personnel played a role in searching for and finalizing subprojects. It does not appear that the hubs or DOE are actively pursuing new subprojects.
In order to do this–and this is a substantial amount of work–DOE would start by engaging in planning meetings with all five of the retained hubs. At minimum, this is weeks or months of ongoing conversations, negotiations, and bargaining about scopes, schedules, and budgets. Further, ideally, these conversations would happen in parallel, but it is questionable how many resources DOE has to draw from, since 3,000 people left under the Deferred Resignation Program. DOE might be forced to triage.
Second, DOE would need to engage its hydrogen experts on staff and at the national labs to figure out what DOE wants and can reasonably expect to get out of a hydrogen hub. This is a surprisingly difficult conversation. Views differ on use cases for hydrogen and have shifted since the Hubs were announced, particularly driven by recent geopolitical shocks in energy markets. As the costs of diesel, jet fuel, and natural gas-derived feedstocks like ammonia soar, alternative fuels like hydrogen are becoming significantly more cost-competitive. This conversation needs deep engagement with the hubs recipients too, of course. DOE and the hubs should take what they know and what they have learned and turn that into a vision of the hydrogen future.
Third, DOE would consult its project management, legal, budget, and contracting experts to chart a reasonable path forward. With recipient cost share, the hubs projects were multi-billion dollar projects. Some had dozens of geographically disbursed work sites. Others expected to shoulder 70% or 80% of the costs. DOE could examine if these project characteristics are still relevant and prudent for 2026. It could also consider if project scopes and subprojects should be changed. In addition, it could determine the cost and schedule trade-offs necessary for Americans to benefit from the hydrogen hubs projects. These questions and a whole host of project specific questions would need to be asked and answered by DOE staff and leadership.
Conclusion
Four months following the April 2026 retention decisions, there is no public proof the Department has directed staff to meaningfully restart the hydrogen hubs. They continue to stall in “ghosted” status, unable to advance their projects and the hydrogen economy. This is a missed opportunity to invest in a hydrogen future and our economy in general.
###
This piece was drafted by trusted and vetted alumni of the U.S. Department of Energy. Any views and opinions expressed are that of the author(s) and do not reflect those of the DOE Alumni Network.